Course Schedule (subject to change)
| week | date | day | topic | readings | notes | presentation | project |
|---|---|---|---|---|---|---|---|
Week 1 |
Sep 7 | Tue | Course introduction, Data warehousing(1) |
[CD97] [GCB+97] | |||
| Sep 9 | Thu | Data warehousing(2) | [ZDN97] | [notes] | |||
Week 2 |
Sep 14 | Tue | No class | ||||
| Sep 16 | Thu | No class | |||||
Week 3 |
Sep 21 | Tue | Data warehousing(3) | ||||
| Sep 23 | Thu | Data mining(1) | [AS94] | [notes] | |||
Week 4 |
Sep 28 | Tue | Data mining(2) | [ZRL96] | |||
| Sep 30 | Thu | Column Stores | [SAB+05] | [notes] | |||
Week 5 |
Oct 5 | Tue | Views(1) | [Hal01] | [notes] | ||
| Oct 7 | Thu | Views(2) | written proposal | Week 6 |
Oct 12 | Tue | Monday schedule |
| Oct 14 | Thu | Views(3) | [KR99] | ||||
Week 7 |
Oct 19 | Tue | Parallel DB | [DGS+90] | [notes] | ||
| Oct 21 | Thu | Parallel Systems(1) | [DG04] | literature survey | |||
Week 8 |
Oct 26 | Tue | Parallel Systems(2) | [CDG+06] | Oct 28 | Thu | Distributed DB | [SAL+96] |
Week 9 |
Nov 2 | Tue | Temporal DB | [BGJ] | |||
| Nov 4 | Thu | Sequence DB | [SLR96] | [notes] | |||
Week 10 |
Nov 9 | Tue | Presentation preparation | ||||
| Nov 10 | Wed | Continuous queries | [HCH+99] | ||||
Week 11 |
Nov 16 | Wed | Data Streams | [ABW06] | [notes] | ||
| Nov 18 | Thu | Data Streams(2) | [AH00] | [notes] | status report | ||
Week 12 |
Nov 23 | Tue | Probabilistic DB(1) | [DS07] | |||
| Nov 25 | Thu | Thanksgiving | |||||
Week 13 |
Nov 30 | Tue | Probabilistic DB(2) | [BSHW06] | |||
| Dec 2 | Thu | Probabilistic DB(3) | [CM05] | ||||
Week 14 |
Dec 7 | Tue | Probabilistic DB(4) | [LD10] | |||
| Dec 9 | Thu | Project Presentation | |||||
Week 15 |
Dec 14 | Tue | |||||
| Dec 16 | Thu | final report |